|
PART 1 –
GENERAL
1.01
REFERENCES
-
Examine all
Drawings for requirements therein affecting the work of this
trade.
1.02 SCOPE
-
In accordance
with the Contract Documents, provide all equipment, material,
labor, and supervision to install a Diaphragm Slurry Wall
foundation system.
-
Construction of
solid reinforced concrete slurry wall including, but not limited
to, the following items:
-
Pre-excavation of
existing obstructions along line of slurry wall and backfilling
with appropriate materials. Excavation of starter trenches and
installation of guide walls.
-
Excavation of
slurry filled slots.
-
Circulation and
maintenance of bentonite slurry.
-
Placing all
keyways and dowels as required for framing and additional sleeves
and anchorage assemblies as required for tiebacks or temporary
bracing.
-
Placing concrete
and reinforcing in the slurry filled slots as shown on the
Drawings.
-
Cleaning of
interior face of wall by raking, brushing, and water jetting, as
excavation proceeds.
-
Cleaning and
patching of all areas of voids, honeycombs, aggregate runs, and
pockets.
-
Clean up and
removal of excavated soil, including removal of bentonite slurry
from site.
-
Grouting and
sealing, as required, to render the wall watertight at construction
joints and other potential locations of leakage.
-
Cutting of all
concrete bulges on the inside face beyond the specified
tolerances.
-
The slurry wall
shall be founded on undisturbed soil strata capable of developing
the bearing capacity indicated on the Drawings. The depth of the
slurry wall has been estimated from the soil borings and some
variation in the depth is to be anticipated.
-
During construction, the
slurry wall is intended as a bulkhead to prevent the ground,
streets, utilities and other structures from damage due to
loss of ground and subsequent movements. The wall's reinforcement
and strength shown on the Drawings, are provided for the
conditions imposed after completion of the slurry wall and all
connecting structural framing and slabs of the completed building.
Temporary loading conditions shall be verified and compensated for
with increased wall reinforcing and/or wall thickness by the
Contractor.
-
In the completed
building, the slurry wall is intended as a basement wall spanning
between floors to retain the surrounding earth, as well as to
transmit the loads to a suitable bearing strata. The inside face of
the slurry wall shall be straight and free from flaws and shall be
watertight. The term “watertight” means that no running water from
the wall or formation of droplets on the wall surface shall be
permitted and that only formation of moist patches -- allowing
water to evaporate from the surface will be
permitted.
1.03 WORKING UNDER OTHER
SECTIONS
-
Work in other
Section related to Slurry Wall Construction:
-
Section ______
Temporary Tieback Construction
-
Section ______
Tieback Testing and Stressing
-
Section ______
Excavation
-
Section ______
Cast-In-Place Concrete
-
Section ______
Structural Steel
-
Coordinate access
to and egress from site with Contractor.
1.04 QUALIFICATIONS
-
Contractor:
Experienced specialty firm having a minimum of 5 years successful
experience installing Work of the same type required for this
project. Employ only skilled tradesmen who are thoroughly
experienced with the materials and equipment to be
used.
-
Contractor’s Soil
Consultant: The Contractor shall retain, at his own expense, the
services of a qualified Soils Consultant to advise him on all
slurry wall construction techniques involved in this Work,
including the design, checking and approvingl of slurry wall items
pertinent to the Work, and construction methods for solution of
problems that may be encountered during the prosecution of the
Work. The Consultant shall be primarily concerned with construction
methods that will result in a finished slurry wall of the required
quality and strength, and with methods that will prevent water
leakage, settlement and/or damage to surrounding structures, roads,
utilities, embankments, both within the property lines and on
adjoining properties.
-
Owner’s Soils
Consultant: The Owner shall retain, at his own expense, a
Consultant to conduct tests and inspections of soil conditions
related to the slurry wall. The Owner’s Soil Consultant shall be
responsible for conducting and interpreting tests. The
inspections shall take the form of a full-time,
continuous inspection of all excavation and panel installation
operations. In addition, the Consultant shall review the
construction methods, equipment, and other pertinent construction
details as furnished by the Contractor.
1.05
QUALITY CONTROL
-
Contractor''s Responsibility
to Facility Quality Control Testing and Inspection.
-
Furnish Owner's Soils
Consultant with a complete set of shop drawings for slurry wall
panels and a complete set of procedures/sequences for slurry wall
installation.
-
Furnish specific
notification, with at least one day's advance notice, for all
slurry wall fabrication and installation
operations.
-
Furnish material samples and
access as required for testing.
-
Furnish access and proper
facilities, including scaffolding, temporary work platforms,
hoisting facilities, as required for inspection of all slurry wall
operations.
-
Furnish labor as required to
facilitate testing and inspection of the Work.
-
Provide storage facilities
for concrete test cylinders.
-
The Contractor will be
responsible for all additional slurry wall inspection and testing
as a consequence of the Work a) not evidencing compliance with this
specification, b) performed with improper supervision, c) performed
without prior notice, or d) performed contrary to standard
construction practice.
-
Owner's Concrete Testing
Agency: The Owner will retain, at his own expense, a testing agency
to perform concrete quality control inspection and testing for the
slurry wall as required.
-
Regulatory Requirements:
Comply with applicable requirements of the laws, codes, ordinances
and regulations of Federal, State and Municipal authorities having
jurisdiction. Obtain necessary approvals form all such
authorities.
-
Surveying:
-
Contractor shall engage a
registered surveyor to perform surveys, layouts, and measurements
for Work. Conduct layout work to lines and levels required and
record actual measurements of horizontal location, bottom and top
elevations, deviations from required tolerances and other data
required for Work.
-
Contractor shall record and
maintain information pertinent to work and cooperate with Owner’s
Soil Consultant to provide data for required slurry wall
reports.
-
Contractor shall install
survey point at 50 ft. maximum spacing along top of wall. Install
at least 1 inclinometer along north, east and west sides of
excavation. Coordinate this work with Owner’s Soils Consultant to
meet regulatory requirements.
-
Contractor shall monitor
survey points and inclinometers weekly during excavation and submit
results to Owner, Architect, Structural Engineer, Owner’s Soils
Consultant, and others designated by Owner.
1.06 STANDARDS
American Society for Testing and Materials (ASTM):
-
-
ASTM A615,
“Specification for Deformed and Plain Billet-Steel Bars for
Concrete Reinforcement”.
-
ASTM C33,
“Specification for Concrete Aggregate”.
-
ASTM C150,
“Specification for Portland Cement”.
-
ASTM D2166, “Test
Methods for Unconfined Compressive Strength of Cohesive
Soil”.
-
ASTM D2216,
“Method for laboratory Determination of Water (Moisture) Content of
Soil, Rock and Soil-Aggregate Mixtures.”
1.07 SUBMITTALS
-
Prepare
submittals as specified in this Section for review and approval by
Owner, Architect, Structural Engineer and Owner’s Soils
Consultant.
-
Satisfactory
proof of installer qualifications.
-
Concrete mix
design: In accordance with Concrete Section ________.
-
Shop Drawings:
Submit shop drawings for the following:
-
Reinforcing
steel.
-
Beam and slab
anchorage plates, details of keyways, and pockets.
-
Bentonite slurry
mix proportions.
-
Engineering
calculations for slurry wall and tiebacks for conditions during
construction; prepared and sealed by a qualified structural
engineer registered in the State of ______________. Calculations
must consider intermediate excavation levels related to tieback
construction.
-
Description of
installation procedures, sequences, panel layouts and provisions
for temporary conditions.
1.08 SITE CONDITIONS
-
Test Boring
Report: Examine the site, the drawings, the record of test borings,
and the subsurface exploration reports prepared by
________________________________, which will be made available by
the Owner to determine all conditions under which the slurry wall
will be installed. The results of test borings are for information
only and are not guaranteed to represent all conditions that will
be encountered.
-
Site Survey: The
survey of the site, existing utilities, and existing construction
prepared by ____________________________________, drawings of any
existing structure that are available through the Owner, which
represent all conditions known to the Owner. Contractor shall
formulate his own conclusions as to the extent of such construction
and shall remove all material of any nature to the design subgrades
indicated or hereinafter specified.
|
|
PART 3 –
EXECUTION
3.01 INSPECTION
-
Examine areas and
conditions under which Work is to occur. Notify Owner immediately,
in writing, of all condition detrimental to proper and timely
completion of Work.
-
Proceed with Work
only after unsatisfactory conditions have been acceptably
remedied.
3.02 PREPARATION
-
Contractor shall
establish:
-
Building layout
lines.
-
Temporary bench
marks.
-
Line and level of
slurry wall panels.
-
Contractor shall
be entirely responsible for, and shall bear the entire cost of
correcting all mislocated slurry wall panels or incorrect cutoff
levels at top of slurry walls.
-
Locate
Utilities:
-
Cooperate with
others to locate utility lines, which might be cut or disturbed
during slurry wall construction.
-
Excavate pits
near ends of lines to determine exact utility
locations.
-
Review proposed
Work with all utilities and arrange for removal, relocation, or
disconnecting and capping of all lines.
-
Contractor has
entire responsibility for cost incurred because of damage to
utilities by its operations.
-
Bracing and
Shoring: Take every precaution and guard against movement or
settlement of the Work, adjacent property, utilities or
improvements. Design and provide bracing tiebacks or shoring
necessary to guard against movement or settlement. The Contractor
shall be entirely responsible for the strength and adequacy of all
tiebacks, bracing and shoring and for the safety and support of
such construction.
-
Before
commencement of operations, and after final Shop Drawings have been
reviewed by the Architect, Structural Engineer and Owner’s Soils
Consultant, arrange for representatives responsible for field
procedures to meet with Architect, Structural Engineer, Contractor
and Owner’s Soils Consultant and Concrete Testing Agency to
finalize all procedures relating to slurry wall
construction.
3.03 INSTALLATION
-
Panel excavation
equipment shall be capable of excavating slots to the required
widths and depths. Equipment shall provide for continuous
excavation through all materials encountered.
-
Provide a stable
suspension of powdered bentonite in water that is adequate to
support the trench sides during excavation. The slurry shall
not produce adverse effects on the tremie concrete in setting
time, density or strength. Density of the slurry shall prevent the
formation of excessive caking.
-
The excavation
shall be filled with a stable suspension of bentonite slurry at all
times and excavating operations shall proceed through the slurry.
Slurry shall be added, as required, to maintain its top level
as excavation operations proceed. The slurry shall be
continuously circulated and cleaned to remove excavated material.
The slurry shall be contained at all times to prevent leakage and
seepage into vaults, basements, utilities and pits. Desanding
equipment shall be required in the slurry cleaning
operations.
-
The panel width
of the wall shall result in a stable excavation condition and be
such as to produce a monolithic wall with continuous concrete
pouring.
-
The vertical
joints formed in the wall panels shall be interlocking and
watertight. The joints shall be completely cleaned to establish
good contact bond between adjacent surfaces.
3.04 TOLERANCES
-
Concrete
Surfaces: The plumb, alignment, and building of the inside face of
the wall shall be limited to a lateral dimension of 2
ฝ-inches
from the theoretical face at any point. All excess material shall
be chipped at the Contractor’s expense. The total out-of-plumb from
the top of the wall to the bottom shall not exceed 1% of the height
at any point in the wall.
-
Reinforcing
Steel: Accurately locate and secure in place before, and during,
placement of concrete. Add steel and spacers necessary to
maintain the shape and location of reinforcing cages. Concrete skid
spacers shall be provided on either side of the cage in order to
hold the reinforcing away from the sides of the trench. The
tolerance in placing the reinforcing steel shall be limited to +/-
1-inch in a direction normal to the wall.
-
Steel Plates,
Keyways and Dowels: Provide for framing members a shown on the
Drawings. The location and tolerances for plates, keyways and
dowels shall not exceed +/- 1 inch in both vertical and horizontal
directions.
3.05 PLACING
CONCRETE
-
Cleaning: Before
placing concrete in the slurry filled trench, the joints of the
next panels shall be thoroughly cleaned to obtain watertight bond.
All loose debris shall be removed by a large capacity airlift
system. Concreting shall not start until the Owner’s Soil
Consultant has verified the required bearing capacity,
cleanliness, and levelness of the bottom.
-
Placement: Place
concrete in the slurry-filled trench by the tremie method, in such
a manner that the concrete displaces the slurry from bottom and
rises in such a manner that mixing of concrete with the
slurry does not occur. The concrete shall be placed through a top
metal hopper and into a rigid leak proof tremie pipe, sufficiently
large enough to permit free flow of concrete. Initially, there
shall be a suitable plug at the bottom of the tremie pipe, which
will not discharge concrete until the concrete head has at least
reached the top level of the slurry.
Alternatively, a “pig” or “rabbit” can be placed in the tremie
pipe, on top of the slurry, after the pipe has been set on the
trench bottom. The “pig” separates the concrete from the slurry.
The pipe should be filled with enough concrete before lifting off
the bottom to release the “pig”. Thereafter, a positive
concrete head will be maintained throughout. The bottom of the
tremie pipe shall remain in the concrete at least 5 feet
and this depth shall be maintained throughout.
The number of tremie pipes in each trench shall be
determined from the requirement that the concrete level shall be
kept horizontal during the pouring operations. No horizontal
movement of the tremie shall be permitted. When the concrete
approaches the top of the slurry wall, dowels shall be set for the
required construction above the wall. The concreting of the panels
shall proceed continuously to the top of the guide walls to produce
a monolithic wall. Cold joints, should they occur, will have to be
rendered watertight by grouting or some other means.
-
Joint Pipe
Removal: The withdrawal of panel joint pipes used at the ends of
the trench, shall be accomplished before the initial setting of
concrete and before any damage to the concrete is likely to occur.
The concrete mix at the time of design shall be checked for setting
time, and retarders added if required to delay the setting time.
Unless retarders are added, the panel joint pipes shall be
withdrawn no later than 45 minutes from the time of placing of
concrete. Controlled, hydraulic jacking of end pipes may be
required.
3.06 SLURRY WALL
CLEANING
-
During earthwork
excavation and after the placement of the slurry wall, clean the
interior wall face using rakes, brushes, or air and water jetting
to remove all bentonite caking and film materials. During this
operation, chip out all interior face wall bulges to within the
stated tolerances. Structurally patch all voids, honeycombed areas,
and areas of exposed reinforcing bars, to provide the required
coverage for reinforcing, and full wall thickness as indicated.
Clean all keyways and embedment items, and bring wall dowels to
their final conditions. Provide internal and external methods of
sealing of the wall to the watertight condition, as previously
indicated for all areas indicated wall leakage including but not
limited to: panel joints, wall penetrations, locations of temporary
tieback system.
3.07 FIELD QUALITY
CONTROL
-
Representative of
slurry wall foundation system installer, qualified to control field
practices, shall be available at all times for detailed control of
procedures and quality.
-
Field Quality
Control Testing by Owner’s Soils Consultant and Concrete Testing
Agency:
-
Concrete: Sample
and test concrete during placement in accordance with
Section_________.
-
Panel
Installation: Provide full time visual inspection of all panel
excavation operations including verification of slurry densities,
slurry cleaning operations, final panel bottom elevation, final
panel cleaning at bottom and at joints, final panel top elevation,
variations in wall location, and variation from plumb.
-
Soil Bearing
Capacity: At the completion of the panel excavation, test and
verify the required soil bearing capacity at the panel bottom.
Owner’s Soils Consultant will interpret the tests and determine if
additional excavation depth is required to achieve the required
soils bearing capacity.
3.08 DISPOSAL OF
SPOIL
-
Clean and
remove water, excavated soil, and bentonite slurry from site.
Dispose of these materials in a manner to avoid endangering public
health, property and portions of work under construction or
completed. Comply with applicable requirements of the laws, codes,
ordinances and regulations of Federal, State and Municipal
authorities having jurisdiction. Obtain necessary permits and
approvals from all such authorities.
|
ทำไม่ไม่แปลให้สำหรับคนที่บางทีเค้าอาจจะไม่สันทัดภาษาล่ะคะ จะทำให้เค้าได้ความรู้บ้าง